It's the last working day of 2016 and the 3D models for the Platform, Jetty & ORF are all ready for the 30% Model Review due to start in the first week of January 2017. The Platform and Jetty will be located off shore about 4km from the port and will be protected from the waves by a breakwater.
We have the model reviews, HAZID, HAZOP & Process SIL all packed into January's schedule. The EPC office here in Seoul is going to be a pretty busy place in January, with our engineering team members from around the world in attendance. The site in Bahrain is ramping up at an accelerated pace, so I have no doubt the emails in the new year will keep us on our toes.
Merry Christmas & Happy New Year.